Home Energy SNEPCo’s Bonga FPSO completes 2022 Turnaround Maintenance

SNEPCo’s Bonga FPSO completes 2022 Turnaround Maintenance

330
0
Bonga FPSO
Access Pensions, Future Shaping

THUR, 17 NOV, 2022-theGBJournal| Shell Nigeria Exploration and Production Company Limited (SNEPCo) announces today that the 2022 Turnaround Maintenance (TAM) of the Bonga floating production storage and offloading (FPSO) has been completed.

The 225kbopd capacity FPSO was shut down on October 18, 2022 to carry out statutory inspections, recertifications and other critical asset integrity restoration activities.

The 2022 TAM which was originally planned for 30 days was completed in 22 days on November 9, 2022 thanks to excellent front-end planning and flawless execution.

‘’Commissioning and start-up activities are in progress and will culminate in ramp up of oil and gas production in the coming days,’’ SNEPCo says in a statement to theG&BJournal

Twitter-@theGBJournal| Facebook-The Government and Business Journal|email: gbj@govbusinessjournal.ng|govandbusinessj@gmail.com

Access Pensions, Future Shaping
5 1 vote
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments