NNPC Ltd., CEO Kyari says Port Harcourt refinery is undergoing regulatory compliance test, to start production in 2 weeks

239
0
Group CEO NNPC Ltd, Mele Kyari (r) appears before Senate Ad hoc Committee
Access Pensions, Future Shaping

FRI, MAR 15 2024-theGBJournal| Group CEO NNPC Ltd, Mele Kyari Thursday told the Senate Ad-hoc Committee that the delivery date of the Port Harcourt and other refineries currently undergoing turn-around maintenance remains sacrosanct.

“We will make sure that promises that we made about the rehabilitation of these refineries are kept. We did a mechanical completion of Port Harcourt refinery in December.

Now, we have crude oil already stocked in it. It is currently undergoing regulatory compliance test before we restream it. I assure you that this refinery will start in next two weeks.

For Warri, we have also done mechanical work on it. It is undergoing regulatory compliance processes that we are doing with our regulators. Kaduna will be ready by December this year, but we have not reached that stage. We believe that it will also be ready on schedule,” the GCEO said.

Kyari explained that currently, Port Harcourt Refinery has received 450,000 barrels of crude for processing following the mechanical completion of the plant in December, last year.

He called for the cooperation of all stakeholders in the rehabilitation process, stressing that “we are all serving this country dutifully and loyally. Nigerians must understand that gradually, we shall get this task done.”

The Senate Ad-hoc Committee is expected to visit the three refineries in Kaduna, Warri and Port Harcourt soon for an on-the-spot assessment of work progress.

X-@theGBJournal|Facebook-the Government and Business Journal|email:gbj@govbusinessjournal.com|govandbusinessj@gmail.com

 

 

Access Pensions, Future Shaping
0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments